Red Cap - Leghoya Wind Farm Development
20 January 2026 | Client: Red Cap Energy (Pty) Ltd
Leghoya Holdings Pty Ltd (Leghoya), an affiliate company of Red Cap Energy (Pty) Ltd (Red Cap) is proposing to develop three Wind Farms and associated infrastructure approximately 6 km North-East of Ermelo, in the Mpumalanga Province. The project is located within the Msukaligwa Local and Gert Sibande District Municipalities. The wind farms will be called the Leghoya 1 Wind Farm, Leghoya 2 Wind Farm and Leghoya 3 Wind Farm. The project includes a network of high voltage transmission lines and substations, to connect the wind farms to the Eskom grid. Collectively the project will be referred to as the ‘Leghoya Wind Farm Development’.
Leghoya has appointed SLR Consulting (South Africa) (Pty) Ltd as the Independent Environmental Assessment Practitioner (EAP) to undertake the required Scoping and EIA (SEIA) processes for the proposed Leghoya Wind Farms and Grid Connection Projects in terms of the EIA Regulation 2014 (as amended) promulgated under (NEMA).
As per the National Environment Management Act (NEMA, Act No. 107 of 1998, as amended) and the 2014 Environmental Impact Assessment (EIA) Regulations (2014 as amended), a Scoping and Environmental Impact Assessment (S&EIA) process is being followed for each wind farm and the grid connection. The formal applications have been submitted to the Competent Authority (CA), Department of Forestry, Fisheries and the Environment (DFFE), and are subject to a joint public participation process (PPP).
Status
The Final Scoping Reports for the above mentioned projects were accepted by DFFE on 5 November 2026.
The Draft EIA Reports for the above-mentioned projects are available for a 30-day public review and comment period from 21 January 2026 - 19 February 2026
Should you and/or your organisation wish to comment on any aspect of the projects, comments should be forwarded to SLR at the email address and telephone number shown above.
A full copy of each EIA Report and appendices are available for download below.
By providing your personal information to submit a comment, you will be included in the SLR an Interested and Affected Party (I&AP) database, and you consent to SLR managing your information in accordance with the Protection of Personal Information Act 4 of 2013. It is assumed that as an I&AP for this Project you authorise SLR to retain and use your Personal Information as part of a contact database for this and/or other Social and Environmental Impact Assessments (ESIA) and that you confirm your acceptance for SLR to contact you regarding this and/or other ESIA processes. SLR will not process your Personal Information, other than as permitted or required by ESIA processes, or as required by law or public policy. SLR will use reasonable, appropriate security safeguards to protect Personal Information, and to reasonably prevent any damage to, loss of, or unauthorised access or disclosure of Personal Information, other than as required for ESIA processes or as required by any Law or public policy. You may request for your Personal Information to be deleted from the I&AP database at any time by contacting SLR.
Non-Technical Summary
Leghoya 1 Wind Farm
- Environmental Impact Assessment Report
- Appendix A - EAP CV & Declaration
- Appendix B - Maps
- Appendix C1 - Specialist Report: Climate Change
- Appendix C2 - Specialist Report: Agriculture
- Appendix C3 - Specialist Report: Aquatic Biodiversity
- Appendix C4 - Specialist Report: Terrestrial Biodiversity
- Appendix C5 - Specialist Report: Bats
- Appendix C6 - Specialist Report: Avifauna
- Appendix C7 - Specialist Report: Visual
- Appendix C8 - Specialist Report: Shadow Flicker
- Appendix C9 - Specialist Report: Noise
- Appendix C10 - Specialist Report: Socio-Economic
- Appendix C11 - Specialist Report: Heritage
- Appendix C12 - Specialist Report: Palaentology
- Appendix C13 - Specialist Report: Traffic
- Appendix C14 - Specialist Report: Aviation
- Appendix C15 - Specialist Report: Biodiversity Offset
- Appendix D1 - Public Participation: Screen Phase Public Participation Report
- Appendix D2 - Public Participation: Scoping Phase Public Participation Report
- Appendix E - DFFE & SSVR
- Appendix F - Additional Information
- Appendix G1 - EMPr - Wind Farm EMPr
- Appendix G2 - EMPr: Overhead Transmission Line EMPr
- Appendix G3 - EMPr: Substation 1A EMPr
- Appendix G4 - EMPr: Substation 1B EMPr
Leghoya 2 Wind Farm
- Environmental Impact Assessment Report
- Appendix A - EAP CV & Declaration
- Appendix B - Maps
- Appendix C1 - Specialist Report: Climate Change
- Appendix C2 - Specialist Report: Agriculture
- Appendix C3 - Specialist Report: Aquatic Biodiversity
- Appendix C4 - Specialist Report: Terrestrial Biodiversity
- Appendix C5 - Specialist Report: Bats
- Appendix C6 - Specialist Report: Avifauna
- Appendix C7 - Specialist Report: Visual
- Appendix C8 - Specialist Report: Shadow Flicker
- Appendix C9 - Specialist Report: Noise
- Appendix C10 - Specialist Report: Socio-economic
- Appendix C11 - Specialist Report: Heritage
- Appendix C12 - Specialist Report: Palaeontology
- Appendix C13 - Specialist Report: Traffic
- Appendix C14 - Specialist Report: Aviation
- Appendix C15 - Specialist Report: Biodiversity Offset
- Appendix D1 - Public Participation: Screening Phase Public Participation Report
- Appendix D2 - Public Participation: Scoping Phase Public Participation Report
- Appendix E - DFFE STR & SSVR
- Appendix F - Additional Information
- Appendix G1 - EMPr: Wind Farm EMPr
- Appendix G2- EMPr: Overhead Transmission Line EMPr
- Appendix G3 - EMPr: Substation 2A EMPr
- Appendix G4 - EMPr: Substation 2B EMPr
Leghoya 3 Wind Farm
- Environmental Impact Assessment Report
- Appendix A - EAP CV & Declaration
- Appendix B - Maps
- Appendix C1 - Specialist Report: Climate Change
- Appendix C2 - Specialist Report: Agriculture
- Appendix C3 - Specialist Report: Aquatic Biodiversity
- Appendix C4 - Specialist Report: Terrestrial Biodiversity
- Appendix C5 - Specialist Report: Bats
- Appendix C6 - Specialist Report: Avifauna
- Appendix C7 - Specialist Report: Visual
- Appendix C8 - Specialist Report: Shadow Flicker
- Appendix C9 - Specialist Report: Noise
- Appendix C10 - Specialist Report: Socio-Economic
- Appendix C1 1- Specialist Report: Heritage
- Appendix C12 - Specialist Report: Palaeontology
- Appendix C13 - Specialist Report: Traffic
- Appendix C14 - Specialist Report: Aviation
- Appendix C15 - Specialist Report: Biodiversity Offset
- Appendix D1 - Public Participation: Screening Phase Public Participation Report
- Appendix D2 - Public Participation: Scoping Phase Public Participation Report
- Appendix E - DFFE STR & SSVR
- Appendix F - Additional Information
- Appendix G1 - EMPr: Wind Farm EMPr
- Appendix G2 - EMPr: Overhead Transmission Line EMPr
- Appendix G3 - EMPr: Substation 3A EMPr
- Appendix G4 - EMPr: Substation 3B EMPr
- Appendix G5 - EMPr: Substation 3C EMPr
Leghoya Grid Connection
- Environmental Impact Assessment
- Appendix A - EAP CV & Declaration
- Appendix B - Maps
- Appendix C1 - Specialist Report: Agriculture
- Appendix C2 - Specialist Report: Aquatic Biodiversity
- Appendix C3 - Specialist Report: Terrestrial Biodiversity
- Appendix C4 - Specialist Report: Avifauna
- Appendix C5 - Specialist Report: Visual
- Appendix C6 - Specialist Report: Socio-Economic
- Appendix C7 - Specialist Report: Heritage
- Appendix C8 - Specialist Report: Palaeontology
- Appendix C9 - Specialist Report: Aviation
- Appendix C10 - Specialist Report: Biodiversity Offset
- Appendix D1 - Public Participation: Screening Phase Public Participation Report
- Appendix D2 - Public Participation: Scoping Phase Public Participation Report
- Appendix E - DFFE STR & SSVR
- Appendix F - Additional Information
- Appendix G1 - EMPr: Overhead Powerline EMPr
- Appendix G2 - EMPr: Switching Substation 1A
- Appendix G3 - EMPr: Switching Substation 1B
- Appendix G4 - EMPr: Switching Substation 2A
- Appendix G5 - EMPr: Switching Substation2B
- Appendix G6 - EMPr: Switching Substation 3A
- Appendix G7 - EMPr: Switching Substation 3B
- Appendix G8 - EMPr: Switching Substation 3C
- Appendix G9 - EMPr: Indawo Collector Station
- Appendix G10 - EMPr: MTS